- Construction Year: 2017
- Community: Credit River Township
- Corridor Served: CH 27
- Project Lead: Scott County
Description
This project will reconstruct the intersection as a roundabout in Credit River Township.
Purpose & Justification
Safety and operational deficiencies will be best addressed with the reconstruction of the intersection as a roundabout.
Project Schedule
An open house was held in January 2016 to introduce the project and provide information on project schedule. Final Construction plans are expected to be completed in November 2016.
View other important dates below:
- Preliminary Design: November 2015 - February 2016
- Final Design: February 2016 - November 2016
- Right-of-Way/Easement Acquisition: 2016
- Construction: Spring 2017