CH 8 & TH 13 Roundabout 

Project Details

  • Construction Year: 2022
  • Community: Spring Lake and Cedar Lake Townships
  • Corridor Served: CH 8, TH 13
  • Project Lead: Scott County/ MnDOT
  • Contractor: TBD
  • Construction Start Date: Spring 2022
  • Local Business Meeting: February 23rd, 2022
  • Public Open House: March 16th, 2022

Description

This project aims improve the safety and operations at the County Highway 8 and Trunk Highway 13 intersection in Spring Lake and Cedar Lake Townships. The project will reconstruct the intersection as a single lane roundabout as part of the MnDOT Trunk Highway 13 pavement rehabilitation project. The two projects will be tied together and are programmed for construction in 2022.

View the Project Page from MnDOT: Hwy 13 Spring Lake and Cedar Lake Townships

Purpose & Justification

 Safety and operational deficiencies will be best addressed with the reconstruction of the intersection as a roundabout.

Project Schedule

  • Preliminary Schedule: Spring 2021
  • Final Design: Summer 2021
  • Right of Way/ Easement Acquisition: Spring 2021- Fall 2021
  • Construction: Spring 2022