2023 Overlays

Project Details

  • Construction Year: 2023
  • Community: Throughout Scott County
  • Project Lead: Scott County
  • Contractor: Valley Paving Inc.
  • Anticipated Completion Date: Fall 2023

Overlay Project (Updated 03/13/23)

CH 03: Between TH 19 and TH 169

  • Location: Belle Plaine 
  • Work Description: Work includes removing the top 4 inches of bituminous, paving the top 4 inches with new bituminous, seal coating, and sign replacement.

CH 03: Between TH 169 and 400 South of Main Street

  • Location: Belle Plaine
  • Work Description: Work includes removing the top 2 inches of bituminous, utility replacement, paving the top 2 inches with new bituminous, seal coating, ADA retrofits, and sign replacement.

CH 04: Between CH 07 and CH 11

  • Location: Township of Belle Plaine 
  • Work Description:  Work includes removing the top 4 inches of bituminous, paving the top 4 inches with new bituminous, seal coating, and sign replacement.

CH 07: Between TH 19 and CH 05

  • Location: Township of Belle Plaine
  • Work Description: Work includes removing all existing bituminous, aggregate base cement stabilization, paving with 5 inches of new bituminous, sealcoating and sign replacement.

CH 02: Intersection of CH 02 and Cedar Lane

  • Location: Townships of Helena and Cedar lake 
  • Work Description: Adding left and right turn lanes.

CH 16: 2,600 Feet West of CH  83 to CH 83

  • Location: Shakopee
  • Work Description: Work includes removing the top 3 inches of bituminous, utility replacement, paving the top 3 inches with new bituminous, seal coating, and sign replacement.

CH 27: Between CH 86 and CH 02

  • Location: Township of New Market
  • Work Description: Work includes removing all existing bituminous, aggregate base cement stabilization, paving with 5 inches of new bituminous, sealcoating and sign replacement. The portion that was reconstructed in 2009 will only receive a 3 inch mill and overlay.

CH 83: Between CH 16 and TH 169 South Ramp

  • Location: Shakopee
  • Work Description: Work includes removing the top 4 inches of bituminous, utility replacement, paving the top 4 inches with new bituminous, seal coating, ADA retrofits, and sign replacement.

CH 83: 430 Feet South of Wilds Path to CH 42

  • Location: Prior Lake
  • Work Description: Work includes removing the top 5 inches of bituminous, utility replacement, paving the top 5 inches with new bituminous, seal coating, and sign replacement.

CH 91: Between CH 02 and CH 08

  • Location: Township of New Market
  • Work Description: Work includes removing all existing bituminous, aggregate base cement stabilization, paving with 5 inches of new bituminous, sealcoating and sign replacement.

Purpose & Justification

This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.  Please drive with caution.

  1. Jake Balk

    Construction Manager

  2. Highway Department


    Physical Address
    200 4th Ave W
    Shakopee, MN 55379

    Phone: : 952-496-8346


Overlays Map

2023 Overlay Map