2020 Overlays CH 6, CH 8, CH 15, CH 27(A) and CH 27(B)

  • Construction Year: 2020
  • Community: Throughout Scott County
  • Project Lead: Scott County
  • Contractor: Valley Paving, Inc.
  • Anticipated Completion: September 2020

Overlay Project

CH 8: From CH 23 to CH 27

  • Start Date: May 19, 2020
  • Traffic Control Changes: CH 8 will be closed starting Mon, June 1, 2020. Road will be open to local residents only during this time. June 30, 2020 Update: Road was paved and reopened to the public. After shoulder and turn lane work concludes, the final wear will be placed. This work is scheduled for next week and traffic should expect some delays during this time. 
  • Work Description: Work includes removal of existing bituminous, cement stabilization 8 inches deep, recycling asphalt and paving new bituminous for a total of 6 inches, and seal coating.
  • Anticipated Completion: July 14, 2020

CH 15: From CH 16 to CH 78

  • Start Date: May 4, 2020
  • Traffic Control Changes: Road open to local traffic only during construction.
  • Work Description:  Work includes removing 3 inches of the existing bituminous, seal coating, and sign replacement.
  • Anticipated Completion: July 13, 2020

CH 15: From CH 78 to CH 14

  • Start Date: May 4, 2020
  • Traffic Control Changes:  Road open to local traffic only during construction.
  • Work Description: Work includes removing all of the approximately 3 inches of bituminous and replacing with 2.5 inches of cold-in-place recycle asphalt, seal coating, and sign replacement. Paving to begin May 15, 2020.
  • Anticipated Completion: July 13, 2020

CH 27(A): From CSAH 16 to CSAH 42

  • Start Date: June 15, 2020
  • Traffic Control Changes: Road open to local traffic only during construction. June 30, 2020 Update: CR 27 was repaved and four lanes were reopened on Sat, June 27. Sealcoat and final striping will occur over the next two weeks.
  • Work Description: Work includes removal and replacement of 4 inches of bituminous, storm sewer maintenance, sign replacements and seal coating. Work also includes intersection pedestrian ramp improvements for ADA compliance.
  • Anticipated Completion: August 14, 2020

CH 27(B): From CSAH 21 to CSAH 68

  • Start Date: July 7, 2020
  • Traffic Control Changes: Road open to local traffic only during construction.
  • Work Description:  Work includes removal of existing bituminous, cement stabilization 8 inches deep, recycling asphalt and paving new bituminous for a total of 6 inches, and seal coating.
  • Anticipated Completion: August 10, 2020


Purpose & Justification

This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.  Please drive with caution.