2019 Overlays on CH 5, CH 53, CH 16, CH 2, CH 89

  • ​Construction Year: 2019
  • Community: Throughout Scott County
  • Project Lead: Scott County
  • Contractor: WM Mueller & Sons, Inc
Overlay Projects 
  


CH 5: From Laredo Ave and Hickory Blvd


  
  • Start Date: June 17, 2019
  • Traffic Control Changes: Road will be open to traffic during construction. Milling will begin on Monday, June 24, 2019.
  • Work Description:  Work includes removing 4.5 inches of the existing bituminous and replacing with 4.5 inches of new bituminous, seal coating, and sign replacement.
  • Completed: July 1, 2019

CH 53: From US Hwy 169 and TH 19


  • Start Date: July 8, 2019
  • Traffic Control Changes: Road will be open to traffic during construction.
  • Work Description: Work includes removing 4 inches of bituminous and replacing with 4 inches of new bituminous, seal coating, and sign replacement.
  • To Be Completed by: July, 2019

CH 16: From Sarazin St and CH 83


  • Start Date: July 8, 2019
  • Traffic Control Changes:  Road will be open to traffic during construction.
  • Work Description: Work includes removing all of the approximately 5 inches of bituminous and replacing with 5 inches of new bituminous, seal coating, and sign replacement.  Intersection pedestrian ramps will be improved for ADA compliance, and the existing bituminous trail along this segment will receive a 1.5 inch overlay and slurry seal.
  • To Be Completed by: July 31, 2019

CH2: From TH 13 and CH 23


  • Start Date: July 22, 2019
  • Traffic Control Changes: Road will be open to traffic during construction.
  • Work Description: Work includes removing 5 inches of the existing bituminous and replacing with 5 inches of new bituminous, sign replacement, and seal coating.
  • To Be Completed by: August 2, 2019

CH 89: From CH 8 to CH 2


  • Start Date: August 5, 2019
  • Traffic Control Changes: Road will be closed during construction.
  • Work Description:  Work includes milling 5 inches of the existing bituminous and replacing with 5 inches of new bituminous, seal coating, and sign replacement.  This work also includes an area of slope repair that consists of full width, full depth reclamation for a length of approximately 450 feet.
  • To Be Completed by: August 30, 2019
      

    Purpose & Justification

    This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.  Please drive with caution.
     
  1. Tulsa Crum

    Construction Supervisor

  2. Highway Department


    Physical Address
    600 Country Trail East
    Jordan, MN 55352


    Directions

    Phone: 952-496-8346

    Hours
    Monday - Friday
    8 a.m. - 4:30 p.m.


Related Documents