2017 Overlay Projects

  • Construction Year: 2017
  • Community: Throughout Scott County
  • Corridors Served: County Highway (CH) 1, 8, 11, 17, 62, 68, 79
  • Project Lead: Scott County

Overlay Projects

CH 1: Between U.S. Highway 169 and 1.8 miles NW

Road will be closed to through traffic.  Local traffic only. Please follow detour.

Start Date: June 26, 2017 (weather permitting)
Completed: Approximately 3 Weeks
   


CH 8: Between TH 13 and CH 23

Road is open to traffic. Please pay attention to work crews as aggregate shouldering and traffic markings will begin June 19, 2017. An alternate route remains in effect.
 
Start Date: May 30, 2017 (weather permitting)
Completed: Approximately 2 weeks
  

CH 11: Between TH 19 and TH 21

Road will be closed to traffic. Local traffic only. Please follow detour.


 


Start Date: June 5, 2017
Completed: Approximately 3 weeks (weather permitting).  Contractor will be removing and replacing the existing asphalt surface.
   

CH 17: Between TH 282 and 500 feet N of Norton Drive

Road is open to traffic.
 


Start Date: May 2, 2017
Completed: May 19th (Weather permitting) completed, 
   

CH 62: Between CH 91 and CH 46


Road will be closed to traffic. Local traffic only. Please follow detour. Please pay attention to work crews as aggregate shouldering and traffic markings will begin June 26, 2017.

Start Date: May 8, 2017
Completed: Contractor scheduled to complete paving operations the week of June 12, 2017 (weather permitting).
  

CH 68: Between CH 27 and the East County line (2 phases)

Phase 1 - CH 91 to Judicial Road


Roadway will remain open to traffic during construction. Expect delays. Please pay attention to work crews as aggregate shouldering and traffic markings will begin June 26, 2017.

Start Date: May 10, 2017
Completion Date: Contractor to work on driveways the week of June 19, 2017 (weather permitting).
   
Phase 2 - CH 91 to CH 27
Roadway will be detoured during construction. Please follow detour. This will remain open to local traffic.   Please pay attention to work crews as aggregate shouldering and traffic markings will begin June 26, 2017.

Start Date: May 24, 2017
Completed: Paving operations completed.  Shoulder work begins the week of June 26, 2017 (weather permitting).
      

CH 79: Between 10th Avenue in City of Shakopee and CH 78

Start Date: TBD
Completed: TBD

Notice to residents who have Driveways located where the work is being done. 
 

Purpose & Justification

This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.