2016 Overlay Projects

  • Construction Year: 2016
  • Community: Throughout Scott County
  • Corridors Served: County Highway (CH) 2, 8, 9, 10, 15, 101
  • Project Lead: Scott County

Overlay Projects



CH 2: Between CH 27 & Elko New Market City Limits

  
Detour Map
Mailbox Notice

Start Date: Week of 8/25/16

Completed: 9/9/2016

   

CH 8: Between CH 27 & CH 91

 
Detour Map
Mailbox Notice

Start Date: 7/11/2016

Completed: 8/25/2016

 

CH 9: Between TH169 & Carver County
 

Detour Map

Start Date: 8/8/201 

Completed: 9/9/2016

CH 10: Between TH 282 and .4 mi South

 

Start Date: 8/8/2016
Completed: 8/29/2016 

CH 15: Between 6th Avenue in Shakopee and CH 16


  
Start Date: 8/16/16 
Completed: 8/29/2016

   

CH 101: West Bound Turn Lane at Shanendoah Drive

Start Date: 9/19/2016
Completed: 9/23/2016

Purpose & Justification


This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.